Analisis Line Balancing Dengan Metode Moodie Young Proses Produksi Pabrik Keripik Kreasi Lutvi Tuntungan 2
Abstract
Kreasi Lutvi Tuntungan II Chips Factory is a cassava chips production company facing significant idle time issues at various workstations. Workstation 2 experiences idle times of 599.87 seconds, 302.19 seconds, and 894.88 seconds. Workstation 3 encounters idle times of 1171 seconds and 138.75 seconds, while Workstation 4 has idle times of 625.56 seconds and 900.48 seconds. These idle times result from substantial disparities between the cycle times in the production line and workstation times. This study uses the Moodie Young method to assess the impact of workstations and idle time on the production line balance at Kreasi Lutvi Tuntungan 2 Chips Factory. The research investigates workstations and idle times to identify congestion and assess production line balance. The study outputs include the production line balance, represented by Balance Delay, Line Efficiency, and Smoothness Index, to determine the overall balance of the production line. The findings indicate suboptimal line efficiency on the actual line, with 4 workstations and 8 work elements achieving a line efficiency of 83%, a Balance Delay of 11.42%, and a Smoothness Index of 1195.85. In contrast, applying the Moodie-Young method results in improved line efficiency at 73.77%, a reduced Balance Delay of 22.06%, and an enhanced Smooth Index of 1798.85. This demonstrates that the Moodie Young method provides a more optimal level of line balancing compared to the existing production line at Kreasi Lutvi Tuntungan 2 Chips Factory.
Keywords
Full Text:
PDFReferences
Andreas Tri Panudju, B. S. (2018). Analisis Penerapan Konsep Penyeimbangan Lini (Line Balacing) Dengan Metode Ranked Position Weight (Rpw) Pada Sistem Produksi Penyamakan Kulit Di Pt. Tong Hong Tannery Indonesia Serang Banten. Jurnal Integritas Sistem Industri, 1.
Angga, M. D. (2017). Analisis Keseimbangan Lintasan (Line Balancing) Pada .
Jurnal Ilmiah Teknik Industri (2017), Vol. 5 No. 2, 77 – 84, 1.
Baroto, T. 2002. Perencanaan Dan Pengendalian Produksi. Jakarta: Ghalia Indonesia.
Dyah Lintang Trenggonowati, N. F. (2019). Mengukur Efisiensi Lintasan Dan Stasiun Kerja. Journal Industrial Servicess, 98.
Harawan Ahyadi, R. S. (2015). Analisis Keseimbangan Lintasan Untuk Meningkatkan. Bina Teknika,Volume 11 Nomor 2, 3.
Iftikar Z. Sutalaksana, R. A. (2006). Teknik Perancangan Sistem Kerja. Kota Bandung: Itb Press.
Kecil, I. S. (2016). Ramon Patrick Karamoy,Petrus Tumade,Indrie Debbie Palandeng. Jurnal Berkala Ilmiah Efisiensi, 2.
- I. S. (2016). Ramon Patrick Karamoy,Petrus Tumade,Indrie Debbie Palandeng. Jurnal Berkala Ilmiah Efisiensi, 3.
K Yin, Robert, 2002. Studi Kasus Desain & Metode. Jakarta: Raja Grafindo Persada
Process, P. S. (N.D.). Derry Rendragraha,Ishardita Pambudi Tama,Ceria Farela Mada Tantrika. Jurnal Rekayasa Dan Manajemen Sistem Industri Vol. 3 No. 3 , 2.
Purnomo, Hari. 2004. Perencanaan & Perancangan Fasilitas. Jakarta: Graha Ilmu
Rubianto, Aris. 2017. Analisis Perancangan Dan Pengukuran Kerja Pada Line Welding Stand Comp Main Type Kzra Untuk Mengoptimalkan Jumlah Operator
DOI: https://doi.org/10.31289/jitmi.v2i2.3419
Refbacks
- There are currently no refbacks.